Most estimating firms will send you a sample once you've handed over your name, email and phone number. Here it is instead. Project and client details are removed; the structure and the rates are untouched.

Division 23 · HVAC

Ductwork takeoff.

Grouped by system, priced per line. Wastage is carried separately so you can see the raw count and the buy quantity side by side. Yellow cells are inputs — change a labor rate and the sheet follows.

Ductwork takeoff — Division 23 Commercial · new construction · TX
Sr.DescriptionQtyWaste Qty + wasteUnitUnit lab hrs Unit mat $Unit lab $Total hrs
Flexible air duct
16" dia flexible air duct, insulated3.6010%3.96LFT0.0853.755.950.34
28" dia flexible air duct, insulated71.9210%79.11LFT0.1005.867.007.91
310" dia flexible air duct, insulated918.5810%1,010.44LFT0.1209.948.40121.25
412" dia flexible air duct, insulated24.6410%27.10LFT0.14513.3010.153.93
Flexible connections
110" dia flexible connection22EA0.32075.0022.400.64
216"×32" flexible connection11EA1.385329.0096.971.39
320"×12" flexible connection157157EA0.840199.0058.80131.88
424"×20" flexible connection1919EA0.900212.0063.0017.10
532"×20" flexible connection66EA1.385329.0096.978.31
636"×12" flexible connection44EA1.520359.00106.406.08
748"×24" flexible connection66EA1.962466.00137.3511.77
Sheet subtotal — labor hours310.60

Air devices, rooftop units, piping and controls follow the same structure on their own sheets. Where a drawing tag is missing, the line says so rather than guessing — you'll see "tag not given" in the description, not a silent assumption.

Division 26 · Electrical

Bid recap.

Every sheet rolls into one recap. Material and labor stay separated the whole way up, tax applies only where it should, and overhead and profit sit on top as their own lines — so a scope review can pull any number apart without you rebuilding the sheet.

Bid recap — Division 26 Multifamily · new construction · TX
Sr.DescriptionMaterialLabor Mat. taxTotal costOverheadProfit
1Residential building A682,9331,182,15444,3911,909,47795,47495,474
2Residential building B613,0431,110,06639,8481,762,95688,14888,148
3Maintenance building5,4977,81635713,670684684
4Trash compactor enclosure3,1914,9282078,326416416
5Amenity pavilion4,1876,11427210,573529529
Totals1,308,8512,311,07785,0753,705,003185,250185,250
Material sales tax 6.5% Overhead 5.0% Profit 5.0% Total with O&P $4,075,503

Tax, overhead and profit percentages are inputs. Yours are probably different — change them and the bid number moves with you.

What else ships

Every job, same three things.

01
Quantity takeoff
Line by line, grouped by system, with quantities you can check against the drawings.
02
Priced recap
Material, labor, tax, overhead and profit, separated and adjustable.
03
Assumptions and exclusions
What we priced, what we didn't, and what we had to assume because the set didn't say. This is the sheet that keeps you out of an argument later.

Delivered as a working spreadsheet, not a locked PDF. Want a full file for your own division? Ask when you send drawings and we'll include one.